well we are some good ole boy directional drillers. We horizontally bore under whatever is in the way with some very large pipe. The job includes mixing mud (betonight) making and breaking down rods and just the job sight itself is usally about 2-18 inches of mud and water. You dont stop unless its lighting so rain and whatever FL. weather there is you work thru it. You dont not go home with a clean spot on you nor a dry spot wether it is from rain, water,or just pure sweat. Right now we are on a 3mth project in Ft. Myers FL. going under I-75 and some surrounding roads with a 42" conduit and shoots are running out about 900' long and 65' deep. Trust me this is some nasty s*@t.